2022-06-06 13:10
Release
2022-06-06 13:10
Budimex finalizes work on the Goleniów-Ciecierzyce gas pipeline, one of the coastal sections of the Baltic Pipeline. In June, one month before the contract deadline, it plans to enter into a technical agreement with investor Gas-Systems. Pudimex said in a statement that permission to occupy must be obtained in July.
As announced, in June and July, gasification and operation of an area of approximately 122 km will be carried out.
In addition to the pipeline, Pudimex has completed four technical facilities: the expansion of the Kolonyov Gas Compressor Station with a piston transmission lock unit and the construction of closure and relief units in Kolonia Kishorovo, Prachivotsi and Pusso.
“We are currently preparing the gas pipe to be connected to the material parts at both ends of the section. The entire pipe has already been laid on the ground and it has passed all the pressure tests. We have completed the line and assembly welding. Start-up will start “- quoted by Pudimex contract manager Schsepen Konobzak in a press release.
According to investor announcements, Baltic pipeline gas exchange is set to begin in October 2022 (PAP Biznes)
Bell / Ana /
“Communicator. Problem solver. Gamer. Passionate writer. Analyst. Avid creator. Lifelong travel maven. Tv evangelist.”
More Stories
Healthy Treats for Happy Hamsters: A Guide to Nutritional Snacks
Poker Pursuit: Unleashing the Skill and Strategy of Casino Card Games!
How to Avoid Accidents While Hunting: Tips and Tricks